Claremont Rail – Cased Crossing – Claremont, WA
Project: Claremont Rail – Cased Crossing Claremont, Western AustraliaCarrier Size: 180mm PE Water MainCasing Size: RCP 500mm (ID)Spacer Model: HDXT-153 (153mm high) Kwik-ZIP® HDXT-153 spacers were installed to facilitatethe slip-lining of a 180mm PE Water Main into an RCP casing for a cased crossing as part of the Claremont Rail Project by GM Microtunnelling. As…

Metro Tunnel – Arden Street Station, Melbourne Victoria
Project: Metro Tunnel – Arden Street Station, Melbourne VictoriaCarrier Size: 225 PVCCasing Size: 370mm BoreSpacer Model: HD-50 (50mm high) Kwik-ZIP® HD-50 spacers were utilised to facilitate the installation of 2 x 10-meter storm water pipes as part of Metro Tunnels development of the new Arden Street Station. kwik-ZIP’s large range of spacers caters for a…

HEB Construction – Waiari Trunk Watermain
Project: Waiari Trunk Watermain Part ALocation: Bay of Plenty, NZInstallation Date: June 2020 Carrier Size: DN710mm PE water pipelineCasing Size: 1040mm steel jacking casingRun Length: 43mSpacer Model: HDXT103 Where are the kwik-Zip spacers being used and why? The kwik-Zip spacers have been installed as part of the Waiari trunk watermain project located in Te Puke,…

Haughton Pipeline Duplication Townsville
Project: Haughton Pipeline Duplication TownsvilleCarrier Size: DN1800 GRPCasing Size: DN2100 RC Jacking PipeRun Length: 54m & 120mSpacer Model: HDX-90 (90mm high) As part of the 36km Haughton Pipeline Duplication Project Kwik-ZIP HDX-90 spacers were used to facilitate the slip-lining of DN1800 GRP Carrier Pipe at 2 locations – a 54m crossing of Woodstock Giru Rd…

Kwik-ZIP to exhibit at Trenchless Middle East 2019
Kwik-ZIP Spacers are pleased to be exhibiting at Trenchless Middle East 2019 on 18-19 February at the Jumeirah Beach Conference & Exhibition Centre in Dubai. Supported by The International Society for Trenchless Technology (ISTT) and The Institution of Civil Engineers (ICE) Trenchless Middle East will attract visitors from the United Arab Emirates, the GCC Countries,…

Rising Sewer Main for Grafton Bridge Utilities Project
Project: Rising Sewer Main for Grafton Bridge Utilities Project Contractor: Ledonne Constructions Pty Ltd Carrier Size: DN375 M-PVC Casing Size: DN600 Mild Steel casing Spacer Model: HDX 65 Kwik-ZIP HDX65 casing spacers were utilised for the Rising Sewer Main for Grafton Bridge Utilities project. The project required two 30m length of DN375 M-PVC carrier pipe…